MICROFIT APPLICATION PROCESS
60 days:
- Applicant submits application via “MicroFIT homepage”
- OPA reviews application for completeness and eligibility
- OPA provides reference number, project location, renewable fuel and project size to municipality
90 Days:
- Applicant requests and receives an offer to connect from their LDC
180 Days:
- OPA issues application approval notice to applicant
- Applicant checks for required approvals with local municipal office (e.g. building permit)
- Applicant constructs their project
- ESA inspects project and issues approval
- LDC connects project
- OPA issues contract to applicant
- Applicant accepts contract and begins receiving microFIT payments