rea-timelines-1024×472

REA Timelines (follow link for description)

Description

REA Timelines

Step 1 (30 days)
Notice of Project or Notice of First Public Meeting
Draft project description report made available
Municipal Consultation Form to Municipality

Step 2
FIRST PUBLIC MEETING

Step 3 (90 days with step 4)
Draft reports made available to municipality

Step 4 (60 days)
Notice of Final Public Meeting
All draft reports made available

Step 5
FINAL PUBLIC MEETING
Developer revises and submits REA application

Step 6 (9 months with step 7)
REA Application accepted and posted on the EBR for a minimum of 30 days
Notice of Application published
All reports posted on developer’s website

Step 7
REA DECISION ISSUED

Aboriginal Consultation (continuous from an early stage in the project) ongoing

Additional Public Meetings (if required) ongoing